CASE STUDY

Production recovery and performance stabilization at a Tier-1 interiors supplier through on-site PMO leadership

Client Description

  • Tier-1 automotive interiors manufacturer with multiple EU /NAF plants supplying seat frames to OEMs
  • High-volume facility with recurring throughput and backlog issues requiring external PMO intervention

Key Challenges

  • Chronic delivery backlogs disrupting OEM production continuity.
  • Low OEE and inconsistent governance driven by poor scheduling, maintenance, and oversight

Approach

  • Deployed an on-site Ambe Program Manager (PMO) to lead production stabilization and performance recovery.
  • Introduced a structured governance model (“mini-plants”) with hourly boards, daily area meetings, and KPI-based escalation.
  • Conducted rapid benchmark assessment identifying >150 gaps; consolidated into 23 project charters across
  • Logistics, Maintenance, Production, and CIP.
  • Implemented task force workstreams, visual management tools, and standardized OEE/downtime reporting.
  • Created a plant-wide roadmap targeting 85% OEE and zero backlog over a 26-week horizon.

Results

  • Stabilized production and restored delivery continuity to OEM
  • Improved plant governance and accountability through daily performance tracking.
  • Launched sustainable improvement system via cross-functional task force ownership.
85% OEE1

target achieved on multiple lines with sustained throughput plus safety stock targets fulfilled


>150Gaps

Consolidated into actionable roadmap and 23 workstream project charters.

1 Production Plan Capacity